Installations of multiwall polycarbonate sheet

1)Note the right way of cold bending and laying;
 
2)Before installing the sheet,take away 5cm wide protection film of the sheet's edge;
  Keep other protection film for protecting the sheet surface during installing.
3)Take away all protection film once finish installing,it's very different to take 
away the film afterLong time outdoor use.
    4)U profile for sealing the open sides of the sheet.
  5)H profile is used to fix two sheets together.  
 
6.We also can use aluminum alloy batten to fix two sheets.
7.Keep enough space at the two sheets' seam: 5mm(summer);8mm(winter)
 
8.The distance of two screws can be adjusted accordingly.Normally it should be
  300-400mm.
 
 

Installations of solid polycarbonate sheet

Before installation
  • Select suitable sheet thickness and allowed bent radius. 
  • Reserve space for heat expansion and watch out for the insert depth (as shown in Table 4). 
  • Do not place PC sheet on the cement ground or against the cement wall. 
  • Clean the frame, keep the inlay surface smooth. 
  • Use appropriate silicone filling and spacer, do not use PVC materials. 
  • If it is necessary to mark on the materials, please mark on the protective film. If the mark has to be
    made directly on the sheet, please use crayon. Do not use sharp object for marking. 
  • Use electric tools (tipped saw) for cutting. When cutting, keep the sheet stabilized to prevent shake, 
    and do not tear off the protective film. 
  • Tear off the protective film only after installation.
Table A
Distance of the width sides (cm) Thickness of the PC sheet (mm) *Amount of insert (mm)
60 3.0 8.0
60-90 4.5 12.7
90-120 6.0 16
120-150 10 19
150-180 12 22.2
180-240 12 25.4
240-300 12 31.8
Design according to 200kg/m2 wind pressure.

Accurate installation 
• Insertion installation • The protective film of inserted part of the frame would affect the adhesiveness of the filling to PC sheet,
 thus, cut out 5-10mm wide protective film of the inserted part.

• Screw installation
  A: When the temperature difference of the outdoor installation is 8C or more, the hole space reserved for 
     bolt or rivet should be larger than bolt diameter 1/16" for heat expansion.
     If the holes distance is 24",the reserved space should be 1/8". When the holes distance is 6", 
     the reserved space should be 1/32" and use rivet for aluminum materials. Do not use tapping screws. 
  B: The top of the rivet should be 1.5-2.0 times larger than the stem, and spaced with a spacer or washer
     to prevent the rivet from pressing the sheet directly. 

  C: All holes should be filled with neutral silicone. Use silicone to coat the outside to prevent cleaner 
     from penetrating the seam and cause cracks. 

  D: Metal trips should be added to the length and width sides, and space for heat expansion should be
     reserved to improve the ability. 

  E: Do not screw over tightly, or it will cause stress. 

  F: Do not use PVC spacer. 

  G: Do not use Primer

Screw  installation

 
ll the information in this technical and installation guide is provided for guidance only
and is given in good faith, but without warranty or guarantee of any kind, whether implied
or expressed.It must be understood that BP PLAST has no control over how the information in this document is perceived and interpreted and therefore cannot be held responsible for any
resulting fabrication or product failure,how's lever caused. Statutory regulations regarding health and safety of operatives's personnels should be strictly adhered to. BP PLAST cannot be responsible for any failure to comply with them. This statement down not affect your statutory rights.

BP PLAST policy is to continually improve products,therefore methods,materials and changes
of specification may be made from time to time without prior notice.This guide is given in good faith and changes may be made without prior notice.